• 2014 Bond Project Update Pictures

    Edgewood:

     

    Edgewood Front Edgewood Main Entrance

    Main Office & New Front Entrance - Completed with only final touches to be added, including permanent carpet installation. The new main entrance stairs and ramp are also complete; the new canopy is also expected to be finished soon.

     

    Edgewood Library Demo      Edgewood Library Demo

     Library - Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018. 

     Edgewood Library Doors

    Library -Hard barriers in place between construction and corridors. Locked doors, hard barrier, plastic seal.

     

    Heathcote: 

    Heathcote MultiPurpose Room Demo    Heathcote Multi Purpose Demo 2

    Multi-Purpose Room -Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018.

    Heathcote Multi Purpose Room     Multi Purpose Room

     Multi-purpose Room - Hard barriers in place between construction and Gym and Old Multi-purpose room . Hard barrier, plastic seal in gym. Plastic covering, brick wall, hard barrier, plastic seal on old Multi-purpose room.

    Heathcote Playground

    Playground -A new playground was installed as part of a plant improvement project in the 2017-18 budget.

     

    Middle School:

    MS Music Wing Outside

    MS Music Wing    MS Music Room

    Instrumental Music Addition - Completed on time for student arrival.

    MS Band Room

    Band Room Renovation - Completed on time for student arrival.

     

    High School:

    HS Learning Commons 1    HS Learning Commons 2

    HS Learning Commons 3       HS Learning Commons 4

    Learning Commons –Work continues in this area. Scheduled to be completed in late November.

    HS iLab

    I-Lab – Close to completion, but unable to be occupied until completion of the Learning Commons enables access.

    HS Fitness Center

    HS Fitness Center   HS Fitness Center

    Fitness Center – Now opened for student use. All major equipment installed and the Center has been cleaned and is safe for occupancy.

    HS Athletics Offices

     Athletic and PE Offices – Completed and open.

    HS Courtyard

    HS Courtyard Drainage –Work continues in these areas. Due to the courtyard’s location in an enclosed area, surrounded by classrooms, work will only occur during non-student hours. We are awaiting an updated schedule based on these shortened work hours; we don’t anticipate this complex project to be finished before the new year.