2014 Bond Project Update Pictures
Edgewood:
Main Office & New Front Entrance - Completed with only final touches to be added, including permanent carpet installation. The new main entrance stairs and ramp are also complete; the new canopy is also expected to be finished soon.
Library - Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018.
Library -Hard barriers in place between construction and corridors. Locked doors, hard barrier, plastic seal.
Heathcote:
Multi-Purpose Room -Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018.
Multi-purpose Room - Hard barriers in place between construction and Gym and Old Multi-purpose room . Hard barrier, plastic seal in gym. Plastic covering, brick wall, hard barrier, plastic seal on old Multi-purpose room.
Playground -A new playground was installed as part of a plant improvement project in the 2017-18 budget.
Middle School:
Instrumental Music Addition - Completed on time for student arrival.
Band Room Renovation - Completed on time for student arrival.
High School:
Learning Commons –Work continues in this area. Scheduled to be completed in late November.
I-Lab – Close to completion, but unable to be occupied until completion of the Learning Commons enables access.
Fitness Center – Now opened for student use. All major equipment installed and the Center has been cleaned and is safe for occupancy.
Athletic and PE Offices – Completed and open.
HS Courtyard Drainage –Work continues in these areas. Due to the courtyard’s location in an enclosed area, surrounded by classrooms, work will only occur during non-student hours. We are awaiting an updated schedule based on these shortened work hours; we don’t anticipate this complex project to be finished before the new year.